On Thu, Jun 28, 2018 at 10:16 PM Paul Belanger
<pabelanger(a)redhat.com>
wrote:
> On Mon, Jun 25, 2018 at 03:33:20PM -0400, Paul Belanger wrote:
> > On Fri, Jun 22, 2018 at 01:00:14PM -0400, Paul Belanger wrote:
> > > Greetings,
> > >
> > > Wanted to give an update to the zuulv3 migration process. As it stands
> right
> > > now, all projects specific to the
rdoproject.org have been fully
> migrated from
> > > jenkins to zuulv3. Hopefully this process was transparent to you, for
> the most
> > > part we were able to fully test everything before flipping the switch
> on a
> > > project. However we did have a few issues with jobs, but thanks to
> jpena,
> > > amoralej and number80, to name a few, we managed to land fixes quickly.
> > >
> > > At this point, we are still waiting to complete the migration of
> tripleo-ci
> > > jobs, this include OVB and various 3rd party CI jobs. We've been
> blocked by a
> > > nodepool migration of upstream-centos-7 nodes, but I'm told that will
> be
> > > finished today. Meaning, we are aiming for Monday morning to flip the
> switch on
> > > the rest of the tripleo-ci specific projects.
> > >
> > > Due to this, we are still converting JJB changes into ansible
> playbooks using
> > > the zuul-migrate command, so I please hold of on moving forward with
> changes to
> > > the new rdo-jobs project. If everything goes well on Monday, we'll
> remove the
> > > freeze on config / rdo-jobs for people to start contributing to again.
> > >
> > > Thanks for your patience during these last 3 weeks, and hopefully
> we'll be
> > > wrapped up Monday. If you have any questions or problems, please
> reply here or
> > > #rdo on freenode.
> > >
> > Next update, today we successfully tested zuulv3 base jobs for devstack
> based
> > tripleo jobs. This basically means we are ready to migrate the remaining
> > tripleo in
rdoproject.org from jenkins to zuulv3. We still need to test
> OVB
> > jobs, but confident they will work.
> >
> > Nodepool capacity has been addressed however we are running into scale
> issues
> > with zuulv3 now. We have an IRC message out to the SoftwareFactory team
> to see
> > about bringing onlne more zuul-executors / zuul-mergers, hopefully this
> will not
> > take long. Once that happens, I finally think we'll be ready to migrate
> the
> > left over tripleo jobs from jenkins to zuulv3.
> >
> Hopefully the last update before we make zuul migration complete.
>
> We've been able to validate tripleo OVB jobs are working correctly under
> zuulv3.
> Since it is now Friday, we won't migrate them from jenkins until early next
> week.
>
> Thanks again for the patience and look forward to sending the all clear
> next
> week.
>
> - Paul
>
Thanks Paul,
We have an odd message showing up in review.openstack from a third party
job atm [1].
Other than that I see things look good w/ third party jobs posting results
to reviews and the logs look good too.
Any idea what the following is caused by?
Thanks for the support!
RDO Third Party CI
Patch Set 4:
Merge Failed.
This change or one of its cross-repo dependencies was unable to be
automatically merged with the current state of its repository. Please
rebase the change and upload a new patchset.
[
1]https://review.openstack.org/#/c/575862
This is likey a result of running out of HDD space on our zuul-executors,
TristanC has added more space. But we are keeping an eye on it.
>
>
> _______________________________________________
> dev mailing list
> dev(a)lists.rdoproject.org
>
http://lists.rdoproject.org/mailman/listinfo/dev
>
> To unsubscribe: dev-unsubscribe(a)lists.rdoproject.org
>
--
Wes Hayutin
Associate MANAGER
Red Hat
<
https://www.redhat.com/>
w <cclayton@redhat.com>hayutin(a)redhat.com T: +1919 <+19197544114>4232509
IRC: weshay
<
https://red.ht/sig>
View my calendar and check my availability for meetings HERE
<
https://calendar.google.com/calendar/b/1/embed?src=whayutin@redhat.com&am...